Logistics facility in Całowanie — precast foundations
A logistics facility built on open ground near Warsaw. The drone photographs show the foundation stage: a grid of socket footings set out for the future structural columns, and the finished slab.
We supplied precast socket footings for the load-bearing columns. A socket footing arrives on site at its final dimensions and, once set, takes the column straight away — with no reinforcing or concreting on site.

- Year of completion:
- 2024
- Use:
- Industrial buildings
- Location:
- Całowanie

Scope of work
The elements were distributed around the site in the order dictated by the column grid, so that the crane could move along the building axis without turning back.
On a building with a large footprint this is the stage that usually decides the programme — precast foundations take the wet trades off the site and make the start of the structural installation independent of the weather.
Scope of work: precast foundation footings, transport and installation on site.




Send us your project — we'll prepare a quote
Dimensioned floor plans, sections and elevations plus the project location. Element selection and a quote in around a week.