
Precast concrete from Poland for Germany, Scandinavia and Slovakia
Formee makes precast concrete in Międzyrzecz in western Poland, 100 km from the German border and about 200 km from Berlin. The factory production control certificates 0761-CPR-1152 and 0761-CPR-1149 were issued by IBMB MPA TU Braunschweig, and the environmental declarations are in the ITB register. To Bernau near Berlin we delivered 2,005 elements on 391 truckloads; erection there was carried out by an erection subcontractor following our delivery sequence. Delivery radius: about 1,000 km, covering Germany, Denmark, Sweden, Czechia and Slovakia.
- 100 km
- from the German border
- 1,000 km
- delivery radius
- 20–50
- truckloads a day from the plant
- MPA Braunschweig
- 0761-CPR certification
Delivered and erected across the border
Figures from the production system: area, elements and truckloads per site. Click through to the project description.
| Project | Place | Year | m² | Elements | Truckloads |
|---|---|---|---|---|---|
| Regeneration of the Bauhaus complex | Bernau bei Berlin, Niemcy | 2025 | 16,103 | 2,005 | 391 |
| Magdeburg Silo — precast balconies and columns | Magdeburg, Niemcy | 2024 | 1,432 | 607 | 57 |
| Single-family house in Žabokreky | Žabokreky, Słowacja | 2025 | 513 | 40 | 6 |
| Single-family house in Kočovce | Kočovce, Słowacja | 2025 | 467 | 31 | 5 |
| Mahút single-family house | Cífer, Słowacja | 2025 | 398 | 41 | 5 |
CE marking under the harmonised standards, assessed in Germany
Conformity assessment under system 2+ was carried out by a German notified body. For Scandinavia, Nordcert certification is added.
- Wall elements
- EN 14992:2007+A1:2012, certificate 0761-CPR-1152, IBMB MPA TU Braunschweig
- Beams and columns
- EN 13225:2013, certificate 0761-CPR-1149, IBMB MPA TU Braunschweig
- Filigree slabs
- EN 13747:2005+A2:2010, declaration of performance 03/26
- Stairs
- Declaration of performance 04/26, factory production control
- Scandinavia
- Nordcert certification since 2022
- Environmental declarations
- ITB-EPD 561/2023 and 562/2023 to EN 15804+A2, in the public ITB register
- Design
- Tekla Structures, shop drawings and IFC models for the client
Truck, permit, sequence
Between 20 and 50 trucks leave the plant every day, usually carrying 22–24 t of elements. Walls travel upright on A-frames, slabs and balconies flat; one truck carries 45–100 m² of wall depending on wall type and weight. Cross-border abnormal loads are planned with permits and travel windows, so the delivery sequence is fixed weeks before erection.
Elements are loaded in erection order and lifted straight from the trailer to the hook, with no site storage. In Bernau, next to listed buildings with a single crane position, we agreed the delivery schedule day by day with site management.
From enquiry to erection
- 1EnquiryDimensioned plans, sections and elevations as PDF, DWG or IFC plus the site location.
- 2Quote in about a weekWith production date, transport and, on request, erection — by our own crews or an erection partner.
- 3Shop drawings in TeklaShop drawings and element plans for approval; connections, cast-in parts and electrical installation are settled here.
- 4ProductionA single-family house in one to three weeks, an apartment building typically in 14 weeks — in parallel with erection.
- 5Delivery and erectionTrucks in erection order, erection by our own crews or an erection partner, or handover to the local shell contractor.
Questions from clients and designers abroad
The most frequent questions from enquiries from Germany.
- Can Polish precast be used in Germany without additional approval?
- Yes, for harmonised products: wall elements to EN 14992, beams and columns to EN 13225 and filigree slabs to EN 13747 carry CE marking with a declaration of performance. Factory production control was certified by IBMB MPA TU Braunschweig (0761-CPR-1152 and 0761-CPR-1149). Structural design follows the Eurocodes with the German national annex.
- What does transport to Germany cost?
- Transport is a line in the quote, not a knock-out criterion: Berlin is about 200 km from the plant, Dresden 250 km, Hamburg 450 km. What matters is the number of trucks, which follows from m² and weight, plus abnormal-load permits. One truck carries 45–100 m² of wall depending on type.
- Does Formee also erect in Germany?
- Yes, with our own crews or with an erection partner. In Bernau near Berlin an erection subcontractor placed the elements following our delivery sequence and crane plan. Alternatively we deliver with erection instructions and element plans to the local shell contractor.
- How long from order to first delivery?
- The quote is ready about a week after complete documents. Production starts once shop drawings are approved; the first elements leave the plant before the last one is cast, because production and erection run in parallel. For an apartment building production typically takes 14 weeks.
- Which language is used for coordination?
- Enquiries, quotes and shop drawings are handled in German and English; drawings are issued as PDF, DWG and IFC from Tekla Structures.
Send us your project — we'll prepare a quote
Dimensioned floor plans, sections and elevations plus the project location. Element selection and a quote in around a week.