Precast in numbers

Square metres, elements, truckloads and production weeks from the plant's production system — for every project with complete data, without marketing rounding.
See the projects

42 projects with production-system data show: the average precast element measures 9.8 m², one truckload carries an average of 54 m² of precast, and producing the full set of elements for an apartment building typically takes 14 weeks. Below is the full table: m², number of elements, truckloads and production time for each project.

177,743
m² of precast
18,087
elements
3,251
truckloads
42
projects with ERP data
Projects

Every site on its own

Rows sorted by precast area, largest first. Click through to the project description.

ProjectPlaceYearCategoryElementsTruckloadsProd. weeksm²/truck
Greeneri Park in ŚwinoujścieŚwinoujście2023Multi-family buildings41,5173,82469811359
Housing estate in PlewiskaPlewiska k. Poznania2024Multi-family buildings16,9491,8493623947
Regeneration of the Bauhaus complexBernau bei Berlin, Niemcy2025Multi-family buildings16,1032,00539112041
Two multi-family buildings in Dąbie — the complete structureDąbie2025Multi-family buildings12,1111,1921863265
Two blocks in Sosnowiec — walls, stairs and balconiesSosnowiec2024Multi-family buildings11,7651,0462482647
Multi-family building in Wojkowice — walls and floor slabsWojkowice2024Multi-family buildings9,3488931562160
Building on Prądzyńskiego StreetWarszawa2025Multi-family buildings8,4428341702050
Housing complex in Chrzanów — precast walls without erectionChrzanów2025Multi-family buildings6,472624911871
Multi-family building in Ostrzeszów — walls, slabs, stairsOstrzeszów2024Multi-family buildings4,807486811959
Multi-family building in Ostrowite — walls and floor slabsOstrowite2023Multi-family buildings4,342415741259
Hussar Loft in Szczecin — precast walls and floor slabsSzczecin2026Multi-family buildings4,223341691561
Multi-family building in Sompolno — layout and tolerancesSompolno2026Multi-family buildings4,13142166963
Multi-family building in Chojnów — walls, slabs, balconiesChojnów2024Multi-family buildings3,619355411488
Guesthouse in Ośno Lubuskie — precast walls and floor slabsOśno Lubuskie2024Multi-family buildings3,618346611459
Two multi-family buildings in Pudliszki — erected in winterPudliszki2026Multi-family buildings3,60937468853
Group of buildings in Tuczno — walls, slabs and balconiesTuczno2026Multi-family buildings3,43333672548
Multi-family building in Mieścisko — walls, slabs, balconiesMieścisko2026Multi-family buildings3,078317491363
Człuchów hospital — extension next to a working wardCzłuchów2026Public buildings2,9632536
Multi-family building in Biała — the next municipalityBiała2026Multi-family buildings1,81618128865
Multi-family building in Człopa — erected in NovemberCzłopa2025Multi-family buildings1,78118732856
Multi-family building in Cienin Kościelny — narrow accessCienin Kościelny2025Multi-family buildings1,73817628662
Logistics facility in Całowanie — precast foundationsCałowanie2024Industrial buildings1,45214932545
Magdeburg Silo — precast balconies and columnsMagdeburg, Niemcy2024Multi-family buildings1,432607571425
Building in Dziwnówek — precast wallsDziwnówek2024Multi-family buildings1,37715826653
Aura in Poznań — architectural concrete facadesPoznań2026Multi-family buildings1,115107461824
Two-storey building in Chludowo — walls, slabs and stairsChludowo2024Office buildings1,063141371529
Hall with office section in Międzyrzecz — columns and wallsMiędzyrzecz2024Industrial buildings6796117940
Single-family house in ŽabokrekyŽabokreky, Słowacja2025Single-family buildings513406386
Single-family house in Wilkszyn built from precast wallsWilkszyn2024Single-family buildings5053910151
Single-family house in KočovceKočovce, Słowacja2025Single-family buildings467315293
Mahút single-family houseCífer, Słowacja2025Single-family buildings398415380
Terraced houses in GójszczGójszcz2023Single-family buildings359545272
Single-family house in Jasieniec — precast wallsJasieniec2024Single-family buildings337274184
Single-family house in Kaźmierz built from precast wallsKaźmierz2024Single-family buildings319224280
Single-family house in Stara Wieś built from precast wallsStara Wieś2024Single-family buildings286293195
Single-family house in Stare Krasnodęby — precast wallsStare Krasnodęby2023Single-family buildings283243194
Single-family house in Kłodawa — precast wallsKłodawaSingle-family buildings267257338
Single-family house in Simoradz built from precast elementsSimoradz2024Single-family buildings249183183
Single-family house in Świecie — precast wallsŚwiecie2023Single-family buildings234173178
Single-family house in Glina — precast wallsGlina2023Single-family buildings2311621116
Single-family house in Klęk — precast wallsKlęk2023Single-family buildings227163176
Precast swimming pool shell in KuźnikKuźnik2023Single-family buildings85102143

A dash means the value is not in the system yet — delivery notes for the newest sites sync with a delay.

By category

House, block, hall

CategoryProjectsElementsm²/elementm²/truckProd. weeks (median)
Multi-family buildings23166,82617,0749.85414
Single-family buildings154,76040911.6731
Public buildings12,96325311.76
Industrial buildings22,13121010.1437
Office buildings11,0631417.52915
What it means

Three numbers that help with planning

Area per truckload. An average of 54 m² per truck is the result for a mix of walls, slabs and balconies. Expanded-clay concrete walls alone travel at 90–100 m² per truck, sandwich walls at 45–55 m²; the weights of each type are listed in the element weight article.

Scale of an apartment building. The 23 buildings in this category average 7,253 m² of precast and 742 elements per building, i.e. 9.8 m² per element. These figures translate directly into crane days and site entries.

Production time. The weeks in the table run from the first to the last element in the production plan, not from the order. Production runs in parallel with erection: the first deliveries leave before the last slab is cast, so production time is not the client's waiting time.

How much does a precast wall weigh? Element weights in kg/m²

Method

Where the numbers come from

The source is the plant's production system (ERP): m² and element counts come from the production plans assigned to the object, truckloads from delivery notes, and production weeks from the first and last element dates in the plan. Figures are not rounded or averaged between sites; projects without complete data are not in the table.

Element counts include walls, slabs, balconies, stairs, beams and columns; auxiliary items such as reinforcement billed by the kilogram are excluded. Truckloads are tractor-trailer sets, usually 22–24 t of elements. The table refreshes together with the project database.

FAQ

Questions about the scale of precast

Answers are calculated from the same table, so they change with it.

How many m² of precast fit on one truckload?
An average of 54 m² per truck across all element types in 42 projects. For walls alone it depends on weight: 15 cm expanded-clay concrete walls travel at 90–100 m², normal-weight concrete at 60–70 m², sandwich walls at 45–55 m². A truck usually carries 22–24 t.
How many precast elements does an apartment building have?
Across the 23 apartment buildings in the table, an average of 742 elements and 7,253 m² of precast per building. The spread is wide, from a few hundred elements in a small social-housing block to several thousand in an apartment complex, which is why each building has its own row.
How long does precast production take for one building?
For an apartment building typically 14 weeks (median) from the first to the last element in the production plan; a single-family house usually takes one to three weeks. Production starts once shop drawings are approved and runs in parallel with erection, so the first elements reach the site long before production ends.
Where do these figures come from and how often are they updated?
From the plant's production system: production plans assigned to the object give m² and element counts, delivery notes give truckloads, production dates give weeks. The data is transferred to the project descriptions by script and refreshed with them; projects without complete data do not enter the table.

Send us your project — we'll prepare a quote

Dimensioned floor plans, sections and elevations plus the project location. Element selection and a quote in around a week.

Call usSend inquiry

Cookies and privacy

We respect your privacy

We use cookies necessary for the website to work. Visit statistics (Google Analytics) are enabled only after your consent.